Bearhawkers
A short update from the Perth Bearcave.
More to follow as it happens...........
A short update from the Perth Bearcave.
- All parts semi inventoried (missing wing struts and for sure some other items, need to talk to Mark G)
- Torque wrenches sent out for calibration
- First wing table finished. Constructed from wing crate with legs welded to the base and particle board screwed to the top. Shelving has been placed below for storage of wing tanks etc
- Fuselage to be moved to the hangar this weekend to make more space in the Bearcave
- Second wing table to be made up in the next week or so.
- Meeting with my technical counsellor (SAAA build advisor) tomorrow morning http://www.saaa.com/
More to follow as it happens...........
Comment