The 2 flap pulleys at station F-L on page 31 of the plans are mounted by welding a piece of 3/8" bushing stock to the nearby tubing. Is this correct and is that enough support for the pulley not to twist and deform with all the load experienced deploying the flaps? Is there more of a support not shown on the plans that others are constructing? Anyone have any pictures? Another question is how far does the flap torque tube extent out from the double root rib? Using the hole for the rear spar attach flange as a reference, where would the flap arm be in relation to this? Thanks
Steve
P203
Steve
P203
Comment